Line I
The first plant was built with technical collaboration from M/S NIHON of Japan and replicated with a five stage pre heater and pre calciner for consistent and superior quality of cement. A purposeful step towards greener technology for cement production has been the installation of Reverse Air Bag House (RABH) technology for reduced pollution and dust free environment at the cement plant. No efforts were spared in commissioning of the second plant in the realm of technology and infrastructure.
Line II
The five stage preheater of the second plant have LP cyclones and ONODA Japan technology calciner installed with kiln capacity is 1500 TPD. The cement mill capacity is 80 TPH. Online gas analysers are installed at pyroprocessing. Closed storage facilities are provided for lime stone, coal and clinker to improve ambient air quality and confirm to environmental precincts. RABH is installed to handle kiln and raw mill dust laden gasses and to maintain low SPM levels in comparison to world standards. ESP is installed to cool exit gases.